Components may be needed for repairs or maintenance after the equipment has been commissioned. The process for selecting and supplying spare parts is therefore part of long-term planning. Euroformat has a dedicated service and spare parts division that works with components for lift equipment.
Frequently asked questions
Answers about selecting, manufacturing, installing, modernising and servicing lift equipment.
Yes, it often does. A greater number of stops and more intensive use can increase the workload on components and the scope of service work. The terms of the maintenance agreement also affect the final cost. It is therefore better to calculate maintenance costs for the specific building.
Yes. A deviation should not be assumed to be insignificant without technical assessment. Its impact depends on the specific shaft parameter and equipment configuration. The actual value should therefore be recorded and provided to the manufacturer, who can assess it in the context of the specific project.
Work that does not affect the shaft may be able to continue. However, finishing work around door openings, shaft walls or adjacent areas may be better postponed if it could make subsequent adjustments more difficult. This should be coordinated with the manufacturer and main contractor to avoid unnecessary rework and delays.
Permitted tolerances are determined by the applicable requirements and the manufacturer’s specifications for the specific lift configuration. They may differ for plan dimensions, pit parameters and shaft verticality. It is therefore better not to rely on general figures. Provide the manufacturer with the actual measurements so they can be assessed against the requirements of the specific lift.
This depends on the nature of the change and the current stage of the specific order. The earlier the manufacturer receives the updated data, the sooner the available options can be assessed. Once a discrepancy has been identified, it is therefore better not to wait until the building works are complete before informing the manufacturer.
Responsibility depends on who carried out the building works and who provided the initial data. If the shaft was built with deviations from the project, responsibility will generally depend on the contractor’s scope of work. If the error is in the drawings themselves, the designer may be responsible. The allocation of responsibility should be clearly defined in the contract before work begins.
A lift cannot be ordered and installed within a few days. Technical approvals, manufacture, delivery and commissioning all require time. A late decision also leaves little time to correct any issues with the shaft. This can lead to downtime, contractual penalties and delays to building commissioning. Ordering early makes the construction programme easier to manage and the budget more predictable.
No. Technical coordination with the manufacturer should begin earlier. Waiting until the building is fully completed leaves less time for equipment selection, checking the shaft parameters and approving documentation. Euroformat works with project data, so cooperation can begin while the building project is still being implemented.
The manufacturer needs the initial project parameters, including information about the shaft, number of stops, doors and required equipment configuration. Euroformat uses a questionnaire to help structure the technical information. The earlier these details are defined, the easier it is to coordinate the subsequent stages with the construction schedule.
Inform the manufacturer immediately and request an updated programme with realistic dates. Review together which stages can be accelerated or carried out in parallel. Any changes should also be coordinated with related building works to avoid additional downtime. The earlier the issue is raised, the more options there are for adjusting the schedule.
Start with the planned installation date and work backwards, allowing time for approvals, manufacture and delivery. Add a contingency for drawing revisions and possible changes to the shaft. Exact lead times depend on the model and the manufacturer’s production schedule, so they should be confirmed in writing. This provides a realistic date for starting the order process rather than an approximate estimate.
Still looking for an answer?
Write to us — an engineer will answer technical questions about your project.