What to check in the lift shaft before ordering a lift: a checklist for developers
Before ordering a lift, it is important to know not only the design dimensions of the shaft but also its actual dimensions. Even small discrepancies can affect the choice of lift cabin, doors and equipment configuration.
Why the actual shaft dimensions should be checked against the project
Drawings show the intended construction, but they do not always reflect exactly what has been built. During construction, door openings may shift, walls may be uneven, or the internal shaft dimensions may differ from the design.
For the developer, the key point is not to provide outdated data to the manufacturer as final. If a lift for a new-build development is being selected for an already completed shaft, it is important to make sure that the drawings correspond to its actual geometry.
Which shaft parameters should be checked before ordering?
Lift selection starts with the building parameters that affect equipment installation. The internal shaft width and depth, pit, top of the shaft, travel height, number of stops and door openings all need to be checked.
The geometry of the structure at different levels also requires particular attention. It is the complete set of these measurements, rather than a single control dimension, that makes it possible to assess whether a particular configuration can be installed.
Shaft width and depth: why one measurement is not enough
A shaft may be wider near the lowest stop and narrower at another level. A single measurement will not reveal this kind of deviation.
The lift shaft should therefore be checked at several points along its height. If the dimensions vary, both the size of the discrepancy and its exact location should be recorded. This helps determine whether the deviation affects the equipment layout.
What to check in the pit
The pit should not be assessed simply by confirming that it exists. The manufacturer needs its actual depth, checked against the project documentation.
If the measurements do not match, the deviation should not be assumed to be acceptable. It should be submitted for technical review together with the other shaft parameters.
How to check the top-floor headroom
The top of the shaft has specific space requirements for the installation of lift equipment. This parameter should therefore be checked using actual measurements rather than relying solely on the building plan.
If discrepancies are found in this area, the manufacturer should receive the updated information before the equipment configuration is approved. Otherwise, compatibility between the equipment and the building structure may only become an issue at a later stage.
Door openings: what to record at each stop
Identical openings on the drawings do not guarantee identical dimensions in the completed building. At each stop, the width, height and position of the opening relative to the shaft should be checked.
It is also important to record the floor where any deviation is found. This gives the manufacturer specific information for technical review rather than a general report that there is a problem.
Why shaft geometry should be checked along the full height
A local narrowing or wall displacement can remain unnoticed if measurements are taken only at the top and bottom of the shaft.
Checking the shaft along its height makes it possible to identify where the actual structure differs from the design. This is important for coordinating the equipment layout and determining what further action may be required.
Which deviations can affect equipment selection?
The greatest attention should be paid to changes in the internal shaft dimensions, pit depth, top-of-shaft dimensions and the position of door openings.
However, a deviation does not automatically mean that the shaft needs to be rebuilt. Its impact on equipment selection is determined after technical assessment, including any possible limitations on lift cabin dimensions or configuration.
What to do if the shaft does not match the drawings
The first step is to stop treating the previous measurements as confirmed data. Control measurements should then be taken, discrepancies recorded and the initial project information updated.
The revised information should be provided to the designer and manufacturer. Following technical review, it can then be determined whether the lift configuration can be adjusted or whether changes to the building structure are required.
What information to prepare for technical selection
The developer should prepare current shaft drawings, measurement results, information on the number of stops, travel height, pit, top-floor headroom and door openings.
Euroformat uses the initial technical data for equipment selection, including through its questionnaire. This helps match the needs of the project with the parameters of the future lift before the final solution is approved.
Developer checklist before ordering a lift
- Check the shaft width and depth at different levels.
- Confirm the actual pit depth and top-floor headroom.
- Record the dimensions of all door openings.
- Check the wall geometry along the full shaft height.
- Confirm the number of stops and travel height.
- Add all deviations from the project to the updated technical data.
- Provide the current information to the manufacturer for technical review.
This checklist helps organise the inspection but does not replace professional measurements or project documentation.
When control measurements are particularly important
They are especially important when the shaft has already been built but the lift has not yet been ordered. In this situation, the equipment can still be selected with the actual condition of the shaft taken into account.
The shaft should also be rechecked if building design decisions changed after the original drawings were prepared. The manufacturer should always receive the latest version of the project data.
How Euroformat works with project technical data
For Euroformat, shaft parameters form part of the initial data used to determine the possible lift configuration. The company’s specialists review drawings, dimensions and equipment requirements for the specific project.
If the developer identifies discrepancies, they should be reported before final approval. This allows the technical solution to be discussed using actual project data rather than assumptions.
When to contact the manufacturer
The manufacturer should ideally be involved during the design stage, while the building parameters can still be coordinated with the lift requirements.
If the shaft has already been completed, the manufacturer should be contacted after control measurements have been taken but before the order is finalised. For a consultation with Euroformat, prepare the current drawings and a record of any identified discrepancies.
Frequently asked questions
Who should measure the lift shaft?
Shaft measurements should be carried out by qualified specialists who understand the requirements for the lift-related building structure and can accurately record its geometry. It is important to check not only the width and depth, but also the pit, top-floor headroom and door openings at every stop. The results should be compared with the project documentation and all discrepancies recorded. Before the equipment configuration is finally approved, this information should be provided to the manufacturer for technical assessment.
Can a lift be ordered using drawings only?
At the design stage, drawings provide the basis for preliminary lift equipment selection. However, once the shaft has been built, the actual dimensions may differ from the design because of construction tolerances or changes made on site. Before the order is finally approved, it is therefore advisable to check the shaft geometry and confirm that the door openings match the project. This allows the lift to be selected using current project data rather than the original documentation alone.
What should you do if the actual shaft is smaller than shown in the project?
First, repeat the measurements and identify the exact levels where the actual dimensions differ from the design. The updated data should then be provided to the designer and Euroformat specialists so that the available technical options can be assessed. Depending on the equipment configuration, changes to its parameters or adjustments to the building structure may be considered. The lift cabin should not be reduced or the shaft altered independently without technical approval.
Can a lift be adapted to an existing shaft?
The possibility of adaptation depends on the actual shaft dimensions, its geometry and the technical requirements of the specific equipment. In some cases, a different lift cabin, door configuration or individual components may be considered, but such changes have technical limits. Euroformat can review the initial project parameters and assess the available configuration options. The final decision is made after checking the compatibility of the equipment with the existing building structure.
Can Euroformat carry out measurements on site?
Euroformat uses shaft parameters and project documentation for the technical selection of lift equipment. However, the availability of an on-site specialist visit specifically to carry out measurements should be confirmed separately, as this is not presented as a universal service for every order. When contacting the company, it is worth providing the project location, current construction stage and available drawings. The company’s representatives can then clarify how the required data should be obtained and whether an on-site measurement visit can be arranged for the specific project.
Conclusion
Incorrect initial dimensions can affect the subsequent selection of the lift. Developers should therefore check not only the shaft width and depth, but also the pit, top-floor headroom, openings and geometry along the full height.
Provide Euroformat with current drawings and measurement results. This makes it possible to discuss the equipment configuration based on the actual conditions of the project.